Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 5)
5.
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
Discussion:
5 comments Page 1 of 1.
Sid said:
6 years ago
I agree with you, Thanks @Bhaskar.
Bhaskar said:
8 years ago
@Puneet:
Optimistic Time: The shortest possible time to complete the activity if everything is going right.
Pessimistic Time: The longest possible time to complete the activity if everything is going wrong.
Optimistic Time: The shortest possible time to complete the activity if everything is going right.
Pessimistic Time: The longest possible time to complete the activity if everything is going wrong.
Rohit said:
8 years ago
Thanks @Puneet Kumar.
Puneet Kumar said:
9 years ago
1) Most Likely time: Most frequently occur if the activity were repeated many times.
2) Pessimistic Time: The shortest possible time to complete the activity if everything is going right.
3) Optimistic Time: The longest possible time to complete the activity if everything is going wrong.
Probabilistic time (Mean of the above three Times) is calculated by given formula.
2) Pessimistic Time: The shortest possible time to complete the activity if everything is going right.
3) Optimistic Time: The longest possible time to complete the activity if everything is going wrong.
Probabilistic time (Mean of the above three Times) is calculated by given formula.
(1)
Fatemeh said:
10 years ago
Why? Please.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers