Discussion Forum : Industrial Engineering and Production Management - Section 3 (Q.No. 10)
10.
Performance rating is equal to
Discussion:
18 comments Page 1 of 2.
Onyinye said:
9 years ago
Normal performance (average worker working at a normal pace)/Observed performance(time measured to complete the task) = Performance rating.
Anbuchelvan said:
6 years ago
Performance rating is equal to Observed performance / Normal performance.
Manoj prasad said:
1 decade ago
Performance rating = normal performance/observed performance.
Harsh Patel said:
9 years ago
Performance Rating = Observed performance/Normal performance.
DHULL said:
8 years ago
Performance Rating = Observed performance/Normal performance.
Muni said:
1 decade ago
Observed performance/Normal performance =Performance rating.
Mubarak AbdulRahman said:
7 years ago
It is Observed Performance/Normal (Standard) Performance.
Rajendra said:
7 years ago
It is Observed performance /normal performance.
Rohit said:
7 years ago
Observed performance/normal performance.
Yogender said:
9 years ago
You are right @Muni. I agree with you.