Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 2)
2.
In time study, the rating factor is applied to determine
standard time of a job
merit rating of the worker
fixation of incentive rate
normal time of a worker
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
28 comments Page 2 of 3.

Kuldip thakkar said:   8 years ago
The correct answer is c.

Ghanshyam Parmar said:   8 years ago
The Correct answer is C.

Vijay said:   8 years ago
The Correct answer is C.

Yogesh said:   8 years ago
I think C is the correct answer.

Rafi said:   8 years ago
Answer c is the correct agree@Aravind.

Arjun said:   1 decade ago
Rating factor is the process during which the time study analyst compares the performance (speed) of the operator observed with the observer's (analyst) own concept of normal performance.

This rating factor is then applied to the observed time to obtain the normal time for the job.

Answer is "D".

Ashu said:   8 years ago
It not asking about the rating factor it is asking why it is applied what is the outcome after applying so in my view, option C is correct.

SANJAY said:   9 years ago
Then, what is mean by fixation of incentive rate?

Lucky said:   9 years ago
Performance Rating can be defined as the procedure in which the time study engineer compares the performance of operator (s) under observation to the Normal Performance and determines a factor called Rating Factor. There are several systems of rating the performance of operator on a job.

So, option "D" is perfect.

Viral said:   9 years ago
The right answer is D.