Discussion Forum : Industrial Engineering and Production Management - Section 3 (Q.No. 19)
19.
In time study, normal time is more than the standard time.
Yes
No
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Ram said:   9 years ago
Standard time = normal time + (normal time x performance factor).

Prashant said:   9 years ago
Standard time = normal time + allowance.

Manoj said:   8 years ago
Here, normal time = standard time + allowance.

Chandru S M said:   6 years ago
Std time =Normal time + allowances.
(1)