Discussion Forum : Industrial Engineering and Production Management - Section 3 (Q.No. 31)
                   
                                       
                                31.
The time taken by a trained worker to perform an operation, while working a steady pace, is known as
 
                                    Discussion:
4 comments Page 1 of 1.
                
                        Wasim said: 
                         
                        7 years ago
                
                Option B is correct.
Standard Time is normal time plus allowances.
                Standard Time is normal time plus allowances.
                        Kalpesh said: 
                         
                        7 years ago
                
                Please explain the given answer.
                
                        Dhaval Chaudhary said: 
                         
                        7 years ago
                
                A is correct answer.
Ref: R S Kurmi.
                Ref: R S Kurmi.
                        Ashutosh Khanvilkar said: 
                         
                        5 years ago
                
                Trained worker to perform an operation, while working a steady pace is called as representative worker. So representative time should be the answer.