24.
At the junction of sewers
top of smaller sewer is kept lower
top of larger sewer is kept lower
tops of both the sewers are at the same level
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
16 comments Page 2 of 2.

Utkarsh said:   5 years ago
C should be the correct option because, during backflow of large sewer, the small sewer can be prevented.

Sanku said:   5 years ago
C is the correct answer.

MJM said:   4 years ago
C is the correct answer. Please correct it.

Thanks.

Arsalan said:   4 years ago
C is the right one.

Sulaiman Khan said:   4 years ago
D is correct, different dia of pipes can be joined together only with manhole.

Prana Krushna said:   4 weeks ago
C is the right answer.