Civil Engineering - Waste Water Engineering - Discussion
Discussion Forum : Waste Water Engineering - Section 3 (Q.No. 24)
24.
At the junction of sewers
Discussion:
16 comments Page 1 of 2.
Prana Krushna said:
4 weeks ago
C is the right answer.
Sulaiman Khan said:
4 years ago
D is correct, different dia of pipes can be joined together only with manhole.
Arsalan said:
4 years ago
C is the right one.
MJM said:
4 years ago
C is the correct answer. Please correct it.
Thanks.
Thanks.
Sanku said:
5 years ago
C is the correct answer.
Utkarsh said:
5 years ago
C should be the correct option because, during backflow of large sewer, the small sewer can be prevented.
Dipu bunku rose said:
6 years ago
@ Hisham is correct. Thanks.
Hisham said:
6 years ago
Crown matching done to avoid back flow from larger to smaller.
(1)
Anirban said:
6 years ago
Yes C is correct as crowns are kept at the same level.
Amjad Ali said:
6 years ago
Not D. C is the correct answer.