Prolongation of chain line across an obstruction in chain surveying, is done by
making angular measurements
drawing perpendiculars with a chain
solution of triangles
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
13 comments Page 2 of 2.

Pramit Samanta said:   4 years ago
Both option B and C are right because in the chain survey we can have a solution of 3-4-5.

Ifra said:   4 years ago
In chain surveying, field work is limited to linear measurements only therefore option B is correct.

Sonu gupta said:   3 years ago
In chain survey,

Linear measurement is only done.

Angular measurement is not done. So the correct answer is B.