41.
In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed
42.
If the shear stress in a R.C.C. beam is
43.
If Sb, is the average bond stress on a bar of diameter d subjected to maximum stress t, the length of the embedment l is given by
44.
On piles, the drop must be at least
45.
The maximum shear stress (q) in concrete of a reinforced cement concrete beam is