10.
If the irrigation efficiency is 80%, conveyance losses are 20% and the actual depth of watering is 16 cm, the depth of water required at the canal outlet, is
Discussion:
33 comments Page 1 of 4.
Farhan said:
2 weeks ago
ir efi = 80% = 0.8.
con efi = 100 - 20 = 0.8,
Overall E = 0.8 * 0.8 = 0.64,
D at outlet = 16/0.64 = 25cm.
con efi = 100 - 20 = 0.8,
Overall E = 0.8 * 0.8 = 0.64,
D at outlet = 16/0.64 = 25cm.
ATUL said:
3 years ago
The Answer is 20cm.
(4)
Shabbir Ahmad said:
3 years ago
The answer here is 20 cm because the depth required at the outlet is asked which is 16/(1-0.2) = 20 cm.
Mistake:
Depth of water at the inlet=20/0.8 = 25 cm.
We might mark an answer as 25 cm but as it is asked at the canal outlet, so 25 cm is not the answer.
Mistake:
Depth of water at the inlet=20/0.8 = 25 cm.
We might mark an answer as 25 cm but as it is asked at the canal outlet, so 25 cm is not the answer.
(5)
Ahmad Mujtaba said:
4 years ago
(100-Efficiency) / (100-Loss) = 0.25.
0.25 x 100.
= 25cm.
0.25 x 100.
= 25cm.
(7)
Shahid said:
4 years ago
0.8x - (0.8x * 0.2) = 16.
Then, x = 25cm.
Then, x = 25cm.
Bishow said:
4 years ago
Let depth at canal be x then 20% loss = x - 20% of x = 0.8x,
From 0.8x only 80% taken by soil that equals 16cm in depth,
So,
80% of 0.8X = 16, Solve x=25.
From 0.8x only 80% taken by soil that equals 16cm in depth,
So,
80% of 0.8X = 16, Solve x=25.
(6)
Shrikant said:
4 years ago
For 80% conveyance efficiency, depth=16cm (means here 20% loss as given in Qs.)
For 100% Conveyance efficiency Depth would be = ((16/80)*100) = 20cm.
Now for 80% irrigation efficiency( as given in QS.) and for 100% conveyance efficiency(as we have calculated above) is =20cm.
=> for 100% irrigation efficiency and 100% conveyance efficiency the required depth will be= ((20/80)*100) = 25cm.
For 100% Conveyance efficiency Depth would be = ((16/80)*100) = 20cm.
Now for 80% irrigation efficiency( as given in QS.) and for 100% conveyance efficiency(as we have calculated above) is =20cm.
=> for 100% irrigation efficiency and 100% conveyance efficiency the required depth will be= ((20/80)*100) = 25cm.
(2)
Amit said:
5 years ago
Overall efficiency (water application efficiency*conveyance efficiency) = {water actually stored to the root zone/water delivered to the field}.
Therefore,
0.8 * 0.8 = 16/x.
So, x = 25cm..
Therefore,
0.8 * 0.8 = 16/x.
So, x = 25cm..
Samim said:
5 years ago
16/(0.8 *0.8) = 25.
80% = 0.8,
100 - 20 % = 0.8.
80% = 0.8,
100 - 20 % = 0.8.
Ghulam mujatab said:
5 years ago
16*.80= 12.8 efficiency,
16*.20= 3.2 loss,
16+(12.8-3.2)=25.6~25.
16*.20= 3.2 loss,
16+(12.8-3.2)=25.6~25.
(1)