Discussion Forum : Hydraulics - Section 2 (Q.No. 4)
4.
A rectangular channel 6 m wide and 3 m deep and having a bed slope as 1 in 2000 is running full. If Chezy's constant C = 54.8, pick up the correct specification of the channel from the following :
Discussion:
15 comments Page 1 of 2.
Swathi said:
2 months ago
R = b*d/b+2*d.
V = c*√r*s.
Q = a*v.
V = c*√r*s.
Q = a*v.
Pkota said:
2 years ago
V = C(mi)^0.5.
m - hyd mean depth A/P.
i-slope.
Q = AV.
m - hyd mean depth A/P.
i-slope.
Q = AV.
Gadadhar said:
3 years ago
Hydraulic radius = 1.5.
Hydraulic mean depth = (area/top width),
= 18/6,
= 3.
Hydraulic mean depth = (area/top width),
= 18/6,
= 3.
Dheeraj kataria said:
3 years ago
@Deep the way you find velocity is wrong.
The correct way to find velocity is v=c (mi) ^0.5.
And.
Rest of the all calculations are correct.
The correct way to find velocity is v=c (mi) ^0.5.
And.
Rest of the all calculations are correct.
UDAYNARAYAN said:
3 years ago
Rec-perimeter (weted) = 3+6+3 = 12m.
Shreedevi said:
4 years ago
Thank you for explaining.
Manjunath said:
4 years ago
Hydraulic depth = area/top width.
H D= 6 * 3/6 = 3m.
But in answer is given hydraulic mean depth is 1.5m this one is hydraulic mean radius.
H D= 6 * 3/6 = 3m.
But in answer is given hydraulic mean depth is 1.5m this one is hydraulic mean radius.
Meron said:
4 years ago
It is an opened channel so there is no one side length.
2b+L=p.
2b+L=p.
Dar Aashu said:
5 years ago
Wetted perimeter =2*h+b,
=2*3+6
=6+6.
P=12.
=2*3+6
=6+6.
P=12.
Abdul Bari said:
5 years ago
Perimeter of rectangular notch = b+2h.
So, 6+(2*3)=12m.
So, 6+(2*3)=12m.