Civil Engineering - Highway Engineering

11. 

If no super elevation is provided on a road along curves, pot holes may develop at

A. inner edge of the road
B. outer edge of the road
C. centre of the road
D. no where on the road.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

12. 

Enoscope is used to determine

A. spot speed
B. average speed
C. travel time
D. none of these.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

13. 

The width of road pavements, depends upon

A. width of traffic lane
B. number of traffic
C. width of median strip
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

14. 

If L is the length of vehicles in metres, C is the clear distance between two consecutive vehicles (stopping sight distance), V is the speed of vehicles in km/hour, the maximum number N of vehicles/hour, is

A.
B.
C.
D.
E.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

15. 

The minimum vertical clearance of overhanging cliffs or any other structure above the surface of a hill road, should be

A. 3 m
B. 4 m
C. 5 m
D. 6 m
E. 4.5 m

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.