For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
25 comments Page 3 of 3.

Rumit Raj said:   3 years ago
Yes, correct. Thanks everyone.
(2)

PRAMOD RAI said:   3 years ago
0.88 m^3 is the correct answer.
(4)

Deepak kumar said:   2 years ago
As per my knowledge, the Correct answer is 0.888 cum.
(4)

Pranjal Saikia said:   2 years ago
Area = 100 M2.
Thickness = 4 cm = 0.04m.
Volume = 100*0.04 = 4 M3.
Add 54% of Dry vol = 4+ 54/100 * 4 = 6.16 m3.
Cement = 1/7 *6.16 = 0.88 m3.
(17)

Birjan rokaya said:   1 year ago
Area =100 m^2.

Thickness = 4cm
= 0.04M
Volume = 100 * 0.04
= 4M^3
The Volume of cement = dry volume/sum of the ratio.
= 1.54/1+2+4
= 0.22 M^3
For 4 m^3 = 0.22*4.
= 0.88M^3.
So ,0.90m^3 is the right answer.
(2)