50.
The detention period in a septic tank is assumed
Discussion:
25 comments Page 1 of 3.
Dileep said:
10 years ago
Can you give me an explanation about this in detailed?
Bhinda said:
9 years ago
I think it should be 36 hours.
Yogi said:
9 years ago
It is 12 to 36 hours.
RAJAN said:
9 years ago
I think it is 24 to 48 hrs.
Vishal said:
9 years ago
It is 12 to 36 hrs.
Naveen said:
8 years ago
It is 12 to 36 hrs.
Himllen said:
8 years ago
It's 24 hours.
Sid said:
8 years ago
It must be in between 24-48 hrs.
SHIVAM DWIVEDI said:
8 years ago
As per IS code specifications the detention period of septic tank is 24 to 48 hours.
Animesh Mahanty said:
8 years ago
24 to 48 hours is correct.