Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 2 (Q.No. 37)
37.
The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is
Rs. 400
Rs. 425
Rs. 450
Rs. 500
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
13 comments Page 2 of 2.

RanguwaL said:   7 years ago
The dimensions in figure are in which unit? mm, m, cm? Please tell me.

RanguwaL said:   7 years ago
According to the answer, the dimensions should be in cm.

So,
Quantity is - (500 cm ) x (400 cm ) x (500 cm) or 5m x 4m x 5m = 20m x 5m =100m
& rate is 450 for %cum means 450 rs for 100cum and answer is 450.
(1)

Saurabh garg said:   7 years ago
E/W= 5 * 0.5 * 0.4 = 1 m3.

The Cost of E/W= 1 * 450 = 450.
(1)