Civil Engineering - Estimating and Costing

Exercise : Estimating and Costing - Section 2
36.
The rate of payment is made for 100 cu m (per % cu m) in case of
Earth work in excavation
Rock cutting
Excavation in trenches for foundation
Earth work in filling the plinth
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

37.
The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is
Rs. 400
Rs. 425
Rs. 450
Rs. 500
Answer: Option
Explanation:
No answer description is available. Let's discuss.

38.
Pick up the incorrect statement from the following:
No deduction is made for the volume occupied by reinforement
No deduction is made for the openings upto 0.1 sq.m
No deduction is made for volumes occupied by pipes, not exceeding 100 sq.cm in cross-section
No deductions are made for the ends of dissimilar structures up to 500 sq.cm cross-sectional area
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

39.
The measurement is made in square metre in case of
Cement concrete in foundation
R.C.C. structure
Hollow concrete block wall
Concrete fencing posts
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

40.
Berms are provided in canals if these are
fully in excavation
partly in excavtion and partly in embankment
fully in embankment
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.