31. 

Pick up the correct statement from the following:

A. In order to check up the average depth of excavation, 'Dead mans' are left at the mid-widths of borrow pits
B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
D. All the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

32. 

The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is

A. 3250 m3
B. 3225 m3
C. 3275 m3
D. 3300 m3

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

33. 

The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

A. 100 mm
B. 150 mm
C. 200 mm
D. 175 mm

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

34. 

Pick up the correct statement from the following:

A. Bricks are paid per thousand
B. Cement is paid per 50 kg bag
C. Lime is paid per quintal
D. Brick aggregates is paid per cum
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

35. 

The weight of an item is measured correct to nearest

A. 0.25 kg
B. 0.50 kg
C. 0.75 kg
D. 1.00 kg
E. 5 kg

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.