Discussion Forum : Estimating and Costing - Section 1 (Q.No. 2)
2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
Discussion:
48 comments Page 4 of 5.
Ravi said:
7 years ago
Can anyone please explain me to get it?
Ravi said:
7 years ago
Can anyone please explain me to get it?
S Raju said:
6 years ago
The value of 1.875 coming from where?
Akshy said:
6 years ago
1 mason 1 day work = 0.1875m^3.
For 2.5cm, it will be(0.1875/0.025) = 7.5m^2.
For 2.5cm, it will be(0.1875/0.025) = 7.5m^2.
(1)
Jithin said:
6 years ago
Can anyone explain on brief with a reference?
Prats said:
6 years ago
As per given building code manuals out-turn for 2.5 cm. 7.5 square metre.
(2)
Hisham said:
6 years ago
Any reference for this?
(1)
Dheeraj said:
6 years ago
If any one know the basic. So please explain.
(1)
Dheeraj kataria said:
6 years ago
Here is mistake in question. That is.
2.5cm thick cement conc. Flooring per person per day = 7.5 sq.m.
2.5cm thick cement conc. Flooring per person per day = 7.5 sq.m.
(1)
Dushyant said:
5 years ago
Explain the correct answer.
(3)