Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 2)
2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
Discussion:
48 comments Page 4 of 5.
Pavan said:
9 years ago
Task work or out turn work both are same.
The capacity of doing work by a skilled labour in the form of work per day is known as task work.
The capacity of doing work by a skilled labour in the form of work per day is known as task work.
Aishwarya rai said:
9 years ago
What is out turn?
Pradosh nayak said:
9 years ago
2.5cm means 0.025M = 1.875/.025=75 sqm. How it is 7.5sqm?
Paritosh said:
9 years ago
I want to know how I can confirm that 'one mason can do concrete flooring of 1.875 m3 per day?
D.Prashanth said:
9 years ago
If one mason can do concrete flooring of 1.875 m3 per day.
So, 1.875/.25 = 7.5 square meter is the correct answer.
So, 1.875/.25 = 7.5 square meter is the correct answer.
VBK said:
10 years ago
By practical experience after trial and error with an average lead and with the help of two helpers one mason can do 7.5 square meter of flooring, NOT by a single Mason.
Mounika said:
10 years ago
I didn't understand.
Can anyone give a clear answer please?
Can anyone give a clear answer please?
Rajashekar said:
1 decade ago
One per person can place the concrete floor per day 1.875 m3.
= 1.875/0.25 = 7.5 M2.
= 1.875/0.25 = 7.5 M2.
M.Areeb said:
1 decade ago
For 100 sum, no. of Mason is 13 no.
i.e for 13 Mason flooring is 100 square meter.
From where you confirm that it is fixed.
i.e for 13 Mason flooring is 100 square meter.
From where you confirm that it is fixed.
Tarun said:
1 decade ago
For 100 sum, no. of Mason is 13 no.
i.e for 13 Mason flooring is 100 square meter.
So for 1 Mason flooring is 100/13 = 7.69 sum.
So option C is the answer.
i.e for 13 Mason flooring is 100 square meter.
So for 1 Mason flooring is 100/13 = 7.69 sum.
So option C is the answer.