Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 2)
2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
Discussion:
48 comments Page 3 of 5.
Sanu chadar said:
5 years ago
Thanks all.
PARASWAR said:
3 months ago
5sqm is the correct answer as per CPWD NORMS.
Shivam Kushawaha said:
2 months ago
7.5 is the right answer.
Deba sarki said:
1 week ago
Thanks everyone for giving explanations.
VBK said:
10 years ago
By practical experience after trial and error with an average lead and with the help of two helpers one mason can do 7.5 square meter of flooring, NOT by a single Mason.
Krish said:
1 decade ago
How it is come?
Sreenivas said:
1 decade ago
Please can anyone tell me how it is find out?
Piya said:
1 decade ago
How is it come?
Jyotitak said:
1 decade ago
Is this mean that A mason can do 7.5 X 2.5= 18.75 Cum of concrete in one day ? is that true? I doubt.
M.Karthick said:
1 decade ago
Mason will do the following process,
1. C, FA, CA shifting after weighing as per Mix design.
2. Hand mixing with water as per mix design.
3. Making homogeneous mix.
4. Making level for every 2.5sqm corner.
5. Laying & levelling concrete as per level point.
6. 7.5 Sqm only is possible.
1. C, FA, CA shifting after weighing as per Mix design.
2. Hand mixing with water as per mix design.
3. Making homogeneous mix.
4. Making level for every 2.5sqm corner.
5. Laying & levelling concrete as per level point.
6. 7.5 Sqm only is possible.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers