Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 2)
2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
Discussion:
48 comments Page 2 of 5.
Dheeraj kataria said:
6 years ago
Here is mistake in question. That is.
2.5cm thick cement conc. Flooring per person per day = 7.5 sq.m.
2.5cm thick cement conc. Flooring per person per day = 7.5 sq.m.
(1)
Jyotitak said:
1 decade ago
Is this mean that A mason can do 7.5 X 2.5= 18.75 Cum of concrete in one day ? is that true? I doubt.
Paritosh said:
9 years ago
I want to know how I can confirm that 'one mason can do concrete flooring of 1.875 m3 per day?
Rajashekar said:
1 decade ago
One per person can place the concrete floor per day 1.875 m3.
= 1.875/0.25 = 7.5 M2.
= 1.875/0.25 = 7.5 M2.
Akshy said:
6 years ago
1 mason 1 day work = 0.1875m^3.
For 2.5cm, it will be(0.1875/0.025) = 7.5m^2.
For 2.5cm, it will be(0.1875/0.025) = 7.5m^2.
(1)
Prats said:
6 years ago
As per given building code manuals out-turn for 2.5 cm. 7.5 square metre.
(2)
Pritam rajak said:
7 years ago
It means the avg floor rough casting of thickness 2.5cm, per Masson/day.
Gawand m. said:
8 years ago
I can't understand the basic behind this. Please explain it clearly.
Milton shaikh said:
7 years ago
It should not understand how can do one masonry per day 1.876?
Mounika said:
10 years ago
I didn't understand.
Can anyone give a clear answer please?
Can anyone give a clear answer please?
Post your comments here: