2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
2.5 sqm
5.0 sqm
7.5 sqm
10 sqm
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
48 comments Page 2 of 5.

Dheeraj kataria said:   6 years ago
Here is mistake in question. That is.

2.5cm thick cement conc. Flooring per person per day = 7.5 sq.m.
(1)

Jyotitak said:   1 decade ago
Is this mean that A mason can do 7.5 X 2.5= 18.75 Cum of concrete in one day ? is that true? I doubt.

Paritosh said:   9 years ago
I want to know how I can confirm that 'one mason can do concrete flooring of 1.875 m3 per day?

Rajashekar said:   1 decade ago
One per person can place the concrete floor per day 1.875 m3.

= 1.875/0.25 = 7.5 M2.

Akshy said:   6 years ago
1 mason 1 day work = 0.1875m^3.

For 2.5cm, it will be(0.1875/0.025) = 7.5m^2.
(1)

Prats said:   6 years ago
As per given building code manuals out-turn for 2.5 cm. 7.5 square metre.
(2)

Pritam rajak said:   7 years ago
It means the avg floor rough casting of thickness 2.5cm, per Masson/day.

Gawand m. said:   8 years ago
I can't understand the basic behind this. Please explain it clearly.

Milton shaikh said:   7 years ago
It should not understand how can do one masonry per day 1.876?

Mounika said:   10 years ago
I didn't understand.

Can anyone give a clear answer please?