Discussion Forum : Estimating and Costing - Section 1 (Q.No. 2)
2.
The expected out turn of 2.5 cm cement concrete floor per manson per day
Discussion:
48 comments Page 5 of 5.
Kesavan V said:
9 years ago
How come this answer?
Ankit said:
8 years ago
.1875/.025 = 7.5sqm.
Satya.M said:
8 years ago
.1875/.025 = 7.5.
Dhadhal purvi said:
3 years ago
18.75/0.25 = 7.5.
(2)
Aishwarya rai said:
9 years ago
What is out turn?
Piya said:
1 decade ago
How is it come?
Krish said:
1 decade ago
How it is come?
Sanu chadar said:
5 years ago
Thanks all.