Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 32)
32.
The expected out turn of 12 mm plastering with cement mortar is
Discussion:
24 comments Page 1 of 3.
Vishnu said:
7 years ago
Here, Expected out turn means = How much square meter of plaster of 12 mm thickness can be done by per mason per day.
Which is taken as 8 square meters per mason per day i.e. it means a Mason is expected to do 8 sqm of plastering of 12 mm thickness per day.
Which is taken as 8 square meters per mason per day i.e. it means a Mason is expected to do 8 sqm of plastering of 12 mm thickness per day.
(1)
Teju said:
9 years ago
The correct answer is 2 cub m for 12 mm plaster.
And 3 cub m for 20 mm plaster.
And 3 cub m for 20 mm plaster.
Aman said:
4 years ago
12mm plastering of cement mortar -8 sq mtr.
So, 8 is the correct answer.
So, 8 is the correct answer.
Abhilasha said:
9 years ago
Can anybody know the method for solving the solution. Please explain it.
Mohammad yasir said:
7 years ago
8 sq mtr is the correct answer. I agree with the given answer.
Kishan Singh said:
8 years ago
It is fixed by PWD.
That a mason can plaster 8 sq mm.
That a mason can plaster 8 sq mm.
Subrata dhua said:
9 years ago
As per estimate book by M. Chakraborty, It is 10 sq m.
Amar said:
9 years ago
How it is calculated? Please give me the explanation.
Lalan said:
7 years ago
The outturn mean efficiency of one Mason is 8sq.m.
Md aftab said:
9 years ago
How it is calculated? Please describe the method.