31.
The most reliable estiamte is
Detailed estimate
Preliminary estimate
Plinth area estimate
Cube rate estimate
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
3 comments Page 1 of 1.

Buch said:   3 years ago
Yes, the detailed estimate is a more reliable estimate than others in this estimate each item of work is fully described with every detailed than other methods.

Dhivya Maniraj said:   9 years ago
Because it only has important estimate than any other estimate.

Utsav said:   7 years ago
Rough estimate is Plinth area estimate.