Civil Engineering - Estimating and Costing - Discussion

Discussion :: Estimating and Costing - Section 1 (Q.No.31)

31. 

The most reliable estiamte is

[A]. Detailed estimate
[B]. Preliminary estimate
[C]. Plinth area estimate
[D]. Cube rate estimate
[E]. None of these.

Answer: Option A

Explanation:

No answer description available for this question.

Dhivya Maniraj said: (Aug 25, 2016)  
Because it only has important estimate than any other estimate.

Utsav said: (Sep 11, 2018)  
Rough estimate is Plinth area estimate.