Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 43)
43.
A critical ratio scheduling
establishes the relative priorities among various activities on a common basis
determines the status of each activity
adjusts automatically changes in activity progress
is a dynamic system
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
20 comments Page 1 of 2.

Vinu Mohandas said:   6 years ago
The critical ratio help in most production scheduling system :.

Determine the status of specific job.

Establish relative priority among jobs on a common basis.

Relate both stock and make-to-order jobs on a common basis.

Adjust priorities (and revise schedules) automatically for changes in both demand and job progress.

Dynamically track job progress and location.

Hima said:   4 years ago
Critical Ratio Scheduling is the Technique for establishing & maintaining priorities among the various jobs of a project.

Hence option A is correct.
(2)

Bhavik said:   6 years ago
The technique for establishing and maintaining priorities among the various jobs of a project is known as?

Please tell me the answer.

Har said:   8 years ago
Critical Ratio = Schedule Performance Index x Cost Performance Index.
CR = SPI x CPI.

Romi said:   6 years ago
Critical Ratio (CR) = Time remaining before due date/Remaining processing time.

Rita said:   9 years ago
Why not 'A'?

As it is used to determining the priorities of various jobs?

Rita said:   9 years ago
Why not 'A'?

As it is used to determining the priorities of various jobs?

Amrit said:   6 years ago
Absolutely right, A is the correct answer. I too agree.

Sabin said:   7 years ago
What is critical ratio? explain anyone.
(1)

Gyan said:   8 years ago
I too think A is the right answer.