43.
A critical ratio scheduling
establishes the relative priorities among various activities on a common basis
determines the status of each activity
adjusts automatically changes in activity progress
is a dynamic system
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
20 comments Page 1 of 2.

Hima said:   4 years ago
Critical Ratio Scheduling is the Technique for establishing & maintaining priorities among the various jobs of a project.

Hence option A is correct.
(2)

Sabin said:   7 years ago
What is critical ratio? explain anyone.
(1)

Somali said:   6 years ago
Here, A is the correct answer.

Beki said:   5 years ago
I think A is the correct answer.

Dipu bunku rose said:   5 years ago
A is the correct answer.

Vinu Mohandas said:   6 years ago
The critical ratio help in most production scheduling system :.

Determine the status of specific job.

Establish relative priority among jobs on a common basis.

Relate both stock and make-to-order jobs on a common basis.

Adjust priorities (and revise schedules) automatically for changes in both demand and job progress.

Dynamically track job progress and location.

Amrit said:   6 years ago
Absolutely right, A is the correct answer. I too agree.

Romi said:   6 years ago
Critical Ratio (CR) = Time remaining before due date/Remaining processing time.

Naveen said:   6 years ago
I think answer A is correct.

Prakash said:   6 years ago
A is the correct option.