1.
Which one of the following represents an activity
Discussion:
16 comments Page 1 of 2.
Sajjad Ali said:
10 months ago
Activity: Has duration, start and end dates and resources assigned.
E.g Excavation, Concrete curing.
Event: Marks the start or end of an activity or group of activities.e.g foundation completion, final inspection etc.
E.g Excavation, Concrete curing.
Event: Marks the start or end of an activity or group of activities.e.g foundation completion, final inspection etc.
Sachin said:
4 years ago
Activity means a consume resources & And has a Definite beginning & end.
The beginning & Completion of an activity.
The beginning & Completion of an activity.
(2)
Said Jamal said:
1 decade ago
Activity means any purposeful and designated task having define resources with ultimate end goal and desired result.
Sujit said:
1 decade ago
Activity means which has particular duration, start, finish and have some resource, so all satisfy this condition.
Hesham bendary said:
1 decade ago
Activity : It is a unit of work break down structure which have a duration and unique purpose to do.
Annoynomous said:
10 years ago
Activity means to do any sort of work, which may include any thing that is physical or mental.
Ch Srinivasa Rao said:
1 decade ago
Activity means certain designated tisk including required resources to complete the same.
Gunjan kunwar said:
1 decade ago
Can you please tell me what is the difference between event and activity?
(1)
David Samuel said:
8 years ago
Activity mean to do work an finish it without remaining.
(1)
Serkeshet shewangizaw said:
1 year ago
Very interesting, Thanks for explaining the answer.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers