Which one of the following represents an activity
excavation for foundation
curing of concrete
setting of question paper
preparation of breakfast
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
16 comments Page 2 of 2.

Sunny said:   1 decade ago
Activity means a particular task in the project.

Hanimo said:   6 years ago
The Correct answer would be option A.

Raj said:   6 years ago
Yeah, agree the correct answer is A.

Merera Tafese said:   3 years ago
The Correct answer is option A.
(2)

Kennedy KeAn Nava said:   10 years ago
How about alternative A?

Hafiz Mumtaz Hussain said:   1 year ago
The Correct answer is A.