Discussion Forum : Construction Management - Section 2 (Q.No. 7)
7.
The critical activity has
Discussion:
3 comments Page 1 of 1.
Priyakarthik said:
7 years ago
I think it is A.
Bharat said:
7 years ago
Yes, it is a maximum float.
Sagar said:
7 years ago
C is correct, A critical path is the longest duration for the completion of a project. It is the path connected by all the critical activities. A critical activity cannot be delayed as delay in critical activity will increase the project completion time therefore critical activity or critical path have zero float or slack.