24.
While scheduling a project by C.P.M.
a project is divided into various activities
required time for each activity is established
sequence of various activities is made according to their importance
net work is drawn by connecting the activities and the events
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.