Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 3)
3.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
1
2
3
4
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Lolla odeh said:   5 years ago
I think the correct answer is 4 cause we have 4 activity each activity need some times to do it.
(1)

MUHAMMAD NABI said:   3 years ago
Concrete work is an activity.

And, The various functions under each activity are shown by one bar on a bar chart.

So, Concrete work is an activity and others are functions.

So, No of bars will be 1.
(7)


Post your comments here: