Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 2 (Q.No. 3)
3.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
Discussion:
12 comments Page 2 of 2.
Lolla odeh said:
5 years ago
I think the correct answer is 4 cause we have 4 activity each activity need some times to do it.
(1)
MUHAMMAD NABI said:
3 years ago
Concrete work is an activity.
And, The various functions under each activity are shown by one bar on a bar chart.
So, Concrete work is an activity and others are functions.
So, No of bars will be 1.
And, The various functions under each activity are shown by one bar on a bar chart.
So, Concrete work is an activity and others are functions.
So, No of bars will be 1.