Discussion Forum : Construction Management - Section 1 (Q.No. 18)
18.
Various activities of a project, are shown on bar charts by
Discussion:
16 comments Page 2 of 2.
Shainy said:
8 years ago
How it is? I thought it is vertical lines also.
Puspendu said:
7 years ago
A is the correct answer. I too agree.
Pawan Raut said:
7 years ago
A is the correct.
Vertical line - Activities Horizontal - Duration.
Vertical line - Activities Horizontal - Duration.
Hayat said:
7 years ago
Right @Pawan Raut.
Suraj bhosale said:
6 years ago
In book vertical line represents various activities of project and horizontal line shows time.
Deeptikant sharma said:
6 years ago
A vertical line shows activities and horizontal line shows time duration.