Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 18)
18.
Various activities of a project, are shown on bar charts by
Discussion:
16 comments Page 2 of 2.
Puspendu said:
7 years ago
A is the correct answer. I too agree.
Pawan Raut said:
7 years ago
A is the correct.
Vertical line - Activities Horizontal - Duration.
Vertical line - Activities Horizontal - Duration.
Hayat said:
6 years ago
Right @Pawan Raut.
Suraj bhosale said:
6 years ago
In book vertical line represents various activities of project and horizontal line shows time.
Ashok Behera said:
5 years ago
Yes, A is correct.
Deeptikant sharma said:
5 years ago
A vertical line shows activities and horizontal line shows time duration.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers