Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 3 (Q.No. 23)
23.
If the effective working time is 7 hours and per batch time of concrete is 3 minutes, the output of a concrete mixer of 150 litre capacity, is
Discussion:
20 comments Page 2 of 2.
123 said:
9 years ago
Why should we consider the efficiency of batching plant as 90%?
Jay Shah said:
1 decade ago
There is any clues for assuming the efficiency = 90%?
Ajay said:
1 decade ago
Can any solve this problem how this answer come?
Rajiv said:
7 years ago
@All.
It is;
54x7/3=126,
Then 126x150 =18900.
It is;
54x7/3=126,
Then 126x150 =18900.
TUHIN said:
6 years ago
100% efficiency can't possible for a machine.
Sumit gawande said:
7 years ago
3*150 = 450.
7*60 = 420.
420*450 = 189000 l.
7*60 = 420.
420*450 = 189000 l.
Chandrbabu said:
9 years ago
Which option is correct?
Please explain it.
Please explain it.
Sailendra said:
5 years ago
Why 90% assumed efficiency? Please explain.
(1)
Hadi said:
4 years ago
How @Rajiv.
Can you explain your answer?
Can you explain your answer?
(2)
Bina said:
1 decade ago
How do this answer came. Please explain ?
Post your comments here: