Civil Engineering - Concrete Technology - Discussion

Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
7 days for beam soffits
14 days for bottom slabs of spans 4.6 m and more
21 days for bottom beams over 6 m spans
2 days for vertical sides of columns
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 4 of 4.

Aliraza said:   6 years ago
Thanks for all.

Archna said:   6 years ago
Thanks all.
(2)


Post your comments here:

Your comments will be displayed after verification.