Civil Engineering - Concrete Technology - Discussion

Discussion Forum : Concrete Technology - Section 3 (Q.No. 4)
4.
Water cement ratio is
volume of water to that of cement
weight of water to that of cement
weight of concrete to that of water
volume of concrete to that of water
both (a) and (b) of the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
15 comments Page 1 of 2.

Mohit said:   8 years ago
In small work, we measure in volume.

And in mass work, we measure in weight to eliminate the bulking of sand.

Therefore E is correct.
(1)

James said:   7 years ago
By weight only. So, the correct Answer is B.
(1)

ANAND KUMAR said:   2 years ago
The correct answer is option ''B''.

(W/C)------> weight of water to the weight of cement.
(1)

William T said:   9 years ago
Is it only weight of water to that of cement?

Vikas said:   9 years ago
How it could be both? Explain clearly.

Prashant dwivedi said:   8 years ago
The correct answer is only B.

Meet Kotadia said:   8 years ago
I think the answer is B.

Dhanu said:   8 years ago
Weight = unit wt * vol.
so A and B correct.

Ajay said:   8 years ago
Weight = Unit Weight x Vol.
Water Unit Weight = 1000 Kg/m3.
But Cement Unit Weight = 1440 Kg/m3.
So, 1000 Kg Water = 1 m3 Water.
But, 1440 Kg Cement = 1m3 Cement.

So, I think Option B is Correct. Weight of Water to Weight of Cement.

Manoj said:   8 years ago
Only B answer is correct.