Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 3 (Q.No. 49)
49.
To hydrate 500kg of cement full water needed, is
Discussion:
30 comments Page 3 of 3.
Vijay said:
8 years ago
23+15=bound water +gel water = full hydration=0.38.
So w/c=0.38=w/500 so w=500 * 0.38=190.
So w/c=0.38=w/500 so w=500 * 0.38=190.
Saifalikhan said:
8 years ago
25% for hyderation and 20% to fill gel pores.
Suresh said:
9 years ago
23% for hydration and 15% to fill gel pores.
(1)
Apcivilian said:
9 years ago
For chemical reaction 23% water needed.
For complete reaction it is 38%.
For complete reaction it is 38%.
(1)
Swapnil pokulwar said:
9 years ago
For 50kg cement, 35 kg water is needed.
So, for 500kg its 135 = 130kg.
So, for 500kg its 135 = 130kg.
Nazira said:
9 years ago
For complete reaction, 38% of water by weight of cement is required.
0.38 * 500 = 190 kg.
But the answer given in this option is 130kg.
How?Can anybody explain?
0.38 * 500 = 190 kg.
But the answer given in this option is 130kg.
How?Can anybody explain?
Sudhansu bhagat said:
9 years ago
24%for Hydration of cement + 15% Jel of water.
So 24 * 500 :- 120liter.
So 24 * 500 :- 120liter.
Soumya choudhury said:
1 decade ago
Actually it is 25% of corresponding water of cement.
So 500*0.25 = 125 kg. But according to option given answer will be 130 kg.
So 500*0.25 = 125 kg. But according to option given answer will be 130 kg.
Amar Deep Tiwari said:
1 decade ago
% wt of water required for full hydration is 26% by wt of cement.
i.e., 26*500/100 = 130 kg.
i.e., 26*500/100 = 130 kg.
Aravind gottumukkala said:
1 decade ago
% wt of water required for full hydration is 38% by wt of cement.
i.e., 38*150/100 = 57 kg.
i.e., 38*150/100 = 57 kg.