29.
For providing a raft foundation, the following activities are involved
The correct sequence is
- ramming the foundation bed
- excavation of the soil upto required depth
- laying the reinforcement over the foundation bed
- curing the cement concrete placed over reinforcement
- pouring the cement concrete over the reinforcement.
The correct sequence is
Discussion:
3 comments Page 1 of 1.
Ashwin said:
1 decade ago
What sequence is this?
Mudasir said:
9 years ago
How raft foundation is done?
Farhan Ullah said:
2 years ago
There should be a "pouring of lean concrete" after ramming of the floor.