For providing a raft foundation, the following activities are involved
  1. ramming the foundation bed
  2. excavation of the soil upto required depth
  3. laying the reinforcement over the foundation bed
  4. curing the cement concrete placed over reinforcement
  5. pouring the cement concrete over the reinforcement.

The correct sequence is
1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4
3, 2, 5, 1, 4.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
3 comments Page 1 of 1.

Farhan Ullah said:   2 years ago
There should be a "pouring of lean concrete" after ramming of the floor.

Mudasir said:   9 years ago
How raft foundation is done?

Ashwin said:   1 decade ago
What sequence is this?