Civil Engineering - Building Construction - Discussion

Discussion Forum : Building Construction - Section 4 (Q.No. 26)
26.
The form work from the sides of beams can be removed only after
1 day
4 days
7 days
14 days.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
6 comments Page 1 of 1.

Homendra said:   3 years ago
It is given "SIDE" of the beam, which can be removed after 1 day.

Only bottom of beam should be removed after 14 days (for span less than 6).
(2)

Er Manoj said:   8 years ago
I think its a wrong statement of this question.

And the right statement is,

The form work from the sides of "COLUMN" can be removed only after ?

How to bear the load if we are remove the frame work of beams its horizontal not in vertical form ?

Please explain me if I am wrong.
(1)

Pushap raj said:   8 years ago
Dosto vertical side of beam and column formwork removed in 24 to 48 hours.
(1)

Praful sl said:   8 years ago
As per IS 456 2000.
Beam more than 6m is 21 days.
Soffit beams after 7 days.
For column it is 1 day.

Pradeep said:   7 years ago
Yes, you are right @Pushap raj.

Manoj kumar yadav said:   4 years ago
Since formwork can be removed from 5sides or faces excluding props, answer may be 7d.