Civil Engineering - Building Construction - Discussion
Discussion Forum : Building Construction - Section 4 (Q.No. 26)
26.
The form work from the sides of beams can be removed only after
Discussion:
6 comments Page 1 of 1.
Er Manoj said:
8 years ago
I think its a wrong statement of this question.
And the right statement is,
The form work from the sides of "COLUMN" can be removed only after ?
How to bear the load if we are remove the frame work of beams its horizontal not in vertical form ?
Please explain me if I am wrong.
And the right statement is,
The form work from the sides of "COLUMN" can be removed only after ?
How to bear the load if we are remove the frame work of beams its horizontal not in vertical form ?
Please explain me if I am wrong.
(1)
Praful sl said:
8 years ago
As per IS 456 2000.
Beam more than 6m is 21 days.
Soffit beams after 7 days.
For column it is 1 day.
Beam more than 6m is 21 days.
Soffit beams after 7 days.
For column it is 1 day.
Pushap raj said:
8 years ago
Dosto vertical side of beam and column formwork removed in 24 to 48 hours.
(1)
Pradeep said:
7 years ago
Yes, you are right @Pushap raj.
Manoj kumar yadav said:
4 years ago
Since formwork can be removed from 5sides or faces excluding props, answer may be 7d.
Homendra said:
3 years ago
It is given "SIDE" of the beam, which can be removed after 1 day.
Only bottom of beam should be removed after 14 days (for span less than 6).
Only bottom of beam should be removed after 14 days (for span less than 6).
(2)
Post your comments here: