Discussion Forum : Building Construction - Section 4 (Q.No. 11)
11.
Pick up the incorrect statement from the following :
Discussion:
5 comments Page 1 of 1.
Rahib said:
5 years ago
Vertical DPC is not provided in internal wall?
Apoorva said:
5 years ago
Yes, right @Rahib.
The vertical DPC is not provided in internal walls.
The vertical DPC is not provided in internal walls.
Atit said:
4 years ago
In my opinion, C will be incorrect.
Rakesh Joshi said:
7 months ago
General Principles While Laying Damp Proof Course:
The damp proofing course should be so laid that it should provide continuous projection.
It should be horizontal or vertical.
A horizontal damp proofing course should cover the full thickness of walls, excluding rendering.
The damp proof course should not be kept exposed on the wall surface, otherwise, it may get damaged during finishing work.
When a horizontal damp proof course is continued to the vertical face, a cement concrete fillet of about 75 mm radius should be provided at the junction.
At junctions and the corners of the walls, the horizontal damp proof course should be laid continuously.
The mortar bed supporting the damp proof course should be even and levelled and should be free from projections so that the damp proofing course is not damaged.
The damp proofing course should be so laid that it should provide continuous projection.
It should be horizontal or vertical.
A horizontal damp proofing course should cover the full thickness of walls, excluding rendering.
The damp proof course should not be kept exposed on the wall surface, otherwise, it may get damaged during finishing work.
When a horizontal damp proof course is continued to the vertical face, a cement concrete fillet of about 75 mm radius should be provided at the junction.
At junctions and the corners of the walls, the horizontal damp proof course should be laid continuously.
The mortar bed supporting the damp proof course should be even and levelled and should be free from projections so that the damp proofing course is not damaged.
Agha Bilal said:
6 months ago
I agree. The given answer Option B is correct.
Post your comments here: