Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option
Explanation:
Whole work is done by A in | ![]() |
20 x | 5 | ![]() |
= 25 days. |
4 |
Now, | ![]() |
1 - | 4 | ![]() |
i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
![]() |
![]() |
1 | - | 1 | ![]() |
= | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
Discussion:
164 comments Page 13 of 17.
Thamaraiselvam said:
1 decade ago
A : 80%
80%\20days = 4%(A's one day work).
And remaining work 20% =3 days(A(4% one day work)+B).
12+B=20
B=8% for 3 days.
80% for 30 days.
96 % for 36 days.
100 for 37 1/2 days :-).
80%\20days = 4%(A's one day work).
And remaining work 20% =3 days(A(4% one day work)+B).
12+B=20
B=8% for 3 days.
80% for 30 days.
96 % for 36 days.
100 for 37 1/2 days :-).
Win's said:
1 decade ago
80% work done by 20 day means 80/20 = 4% per day by A.
So 100/4 = 25 day for A.
He took B to do the remaining 20% task in three day.
Means A's contributions is 12% and B's 8% in three days.
So now B = 100/8*3 = 37.5 that's it.
So 100/4 = 25 day for A.
He took B to do the remaining 20% task in three day.
Means A's contributions is 12% and B's 8% in three days.
So now B = 100/8*3 = 37.5 that's it.
Sanjeev pandey said:
1 decade ago
23(1/25) + 3(1/B) = 1 .....(1).
B = 75/2 Days.
B = 75/2 Days.
Srujan said:
1 decade ago
Am getting troubled like this questions, can any one knows the tricks to solve these kind of problems.
VIKRAM SIHAG said:
1 decade ago
Efficeny of A+B = 20/3 = 6.66.
EFFICENCY OF A = 80/20 = 4.00.
THEN EFFICENCY OF B = 6.66-4.00 = 2.66.
DAYS TAKEN BY B = 100/2.66 = 37.5.
EFFICENCY OF A = 80/20 = 4.00.
THEN EFFICENCY OF B = 6.66-4.00 = 2.66.
DAYS TAKEN BY B = 100/2.66 = 37.5.
Sravya said:
1 decade ago
80% ------ 20 days.
100% ----- ?.
(20/80)*100 = 25 days.
A can complete 100% work in 25 days.
Remaining (120% work (A&B))similarly,
20%----- 3 days.
100%----- ? we get 15 days(1/15 work per day).
we know that A+B = 1/15.
B = 1/15 - 1/25 : Option C.
100% ----- ?.
(20/80)*100 = 25 days.
A can complete 100% work in 25 days.
Remaining (120% work (A&B))similarly,
20%----- 3 days.
100%----- ? we get 15 days(1/15 work per day).
we know that A+B = 1/15.
B = 1/15 - 1/25 : Option C.
Ravi parashar said:
1 decade ago
Short Cut. This method you can do orally.
A is able to save two days which means that this is the work done by B actually in 3 days. Which turns out to be.
A 2 days work = 8 which is equal to 3 days work of B.
B in 3 days does 8 unit of work.
B in 100 days will do (3/8) *100 = Option C.
A is able to save two days which means that this is the work done by B actually in 3 days. Which turns out to be.
A 2 days work = 8 which is equal to 3 days work of B.
B in 3 days does 8 unit of work.
B in 100 days will do (3/8) *100 = Option C.
Shivaram goud said:
1 decade ago
@Snehagoud.
Can you check the what is 80/100 = 5/4?
Can you check the what is 80/100 = 5/4?
Seema duhan said:
1 decade ago
A = (1/20)*(80%) = (1/20)*(80/100) = 1/25. (EQUATION 1).
Remaining work=100%-80%=20%.
A+B=(1/3)*(20%)=(1/3)*(20/100)=1/15. (EQUATION 2).
Put equation 1 in equation 2, we get:
(1/25)+B = 1/15.
B = 2/75.
So B alone can do this work in 75/2 days.
Remaining work=100%-80%=20%.
A+B=(1/3)*(20%)=(1/3)*(20/100)=1/15. (EQUATION 2).
Put equation 1 in equation 2, we get:
(1/25)+B = 1/15.
B = 2/75.
So B alone can do this work in 75/2 days.
Balaji said:
1 decade ago
I can't understand the simple step anyone friends tell me (1/15-1/25) please tell me?
Post your comments here: