Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
164 comments Page 13 of 17.

Thamaraiselvam said:   1 decade ago
A : 80%

80%\20days = 4%(A's one day work).

And remaining work 20% =3 days(A(4% one day work)+B).
12+B=20

B=8% for 3 days.
80% for 30 days.

96 % for 36 days.
100 for 37 1/2 days :-).

Win's said:   1 decade ago
80% work done by 20 day means 80/20 = 4% per day by A.

So 100/4 = 25 day for A.

He took B to do the remaining 20% task in three day.

Means A's contributions is 12% and B's 8% in three days.

So now B = 100/8*3 = 37.5 that's it.

Sanjeev pandey said:   1 decade ago
23(1/25) + 3(1/B) = 1 .....(1).

B = 75/2 Days.

Srujan said:   1 decade ago
Am getting troubled like this questions, can any one knows the tricks to solve these kind of problems.

VIKRAM SIHAG said:   1 decade ago
Efficeny of A+B = 20/3 = 6.66.
EFFICENCY OF A = 80/20 = 4.00.

THEN EFFICENCY OF B = 6.66-4.00 = 2.66.

DAYS TAKEN BY B = 100/2.66 = 37.5.

Sravya said:   1 decade ago
80% ------ 20 days.
100% ----- ?.

(20/80)*100 = 25 days.

A can complete 100% work in 25 days.

Remaining (120% work (A&B))similarly,

20%----- 3 days.
100%----- ? we get 15 days(1/15 work per day).

we know that A+B = 1/15.

B = 1/15 - 1/25 : Option C.

Ravi parashar said:   1 decade ago
Short Cut. This method you can do orally.

A is able to save two days which means that this is the work done by B actually in 3 days. Which turns out to be.

A 2 days work = 8 which is equal to 3 days work of B.

B in 3 days does 8 unit of work.

B in 100 days will do (3/8) *100 = Option C.

Shivaram goud said:   1 decade ago
@Snehagoud.

Can you check the what is 80/100 = 5/4?

Seema duhan said:   1 decade ago
A = (1/20)*(80%) = (1/20)*(80/100) = 1/25. (EQUATION 1).

Remaining work=100%-80%=20%.

A+B=(1/3)*(20%)=(1/3)*(20/100)=1/15. (EQUATION 2).

Put equation 1 in equation 2, we get:
(1/25)+B = 1/15.
B = 2/75.

So B alone can do this work in 75/2 days.

Balaji said:   1 decade ago
I can't understand the simple step anyone friends tell me (1/15-1/25) please tell me?