9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option
Explanation:
Whole work is done by A in | ![]() |
20 x | 5 | ![]() |
= 25 days. |
4 |
Now, | ![]() |
1 - | 4 | ![]() |
i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
![]() |
![]() |
1 | - | 1 | ![]() |
= | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
Discussion:
164 comments Page 17 of 17.
Jay said:
1 decade ago
@shefali..the 15 days is nothing but remaining work probability. 4/5 i.e 80% work is done by A so remaining is 1-(4/5)= 1/5. its same like p+q=1 in probability.
n same like 3*5=15 days
n same like 3*5=15 days
(1)
Shefali said:
1 decade ago
How do we get that A & B together can do work in 15 days?
Snehagoud said:
1 decade ago
A did only 80% of work out of total work in 20 days so
work done by A=80/100=5/4
so total workdone by A=20*5/4
work done by A=80/100=5/4
so total workdone by A=20*5/4
SIVARANJANI said:
1 decade ago
Sorry I can't get it why we should multiply with that 5/4 ?
(2)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers