Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 28)
28.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

13 1 days
3

15 days
20 days
26 days
Answer: Option
Explanation:

Work done by X in 8 days = ( 1 x 8 ) = 1 .
40 5

Remaining work = ( 1 - 1 ) = 4 .
5 5

Now, 4 work is done by Y in 16 days.
5

Whole work will be done by Y in ( 16 x 5 ) = 20 days.
4

Therefore X's 1 day's work = 1 , Y's 1 day's work = 1 .
40 20

(X + Y)'s 1 day's work = ( 1 + 1 ) = 3 .
40 20 40

Hence, X and Y will together complete the work in ( 40 ) = 13 1 days.
3 3

Discussion:
33 comments Page 4 of 4.

Anonymous said:   4 years ago
@All.

For those who are asking why 5/4 is multiplied,

Let's take an example, Suppose You complete work 1/2 of a work in 2 days. In how much time will you complete the entire work. 4 days right, how did you get it? you multiplied 2.

Eg:

1/2 : 2 is as 1: x, (I took 1 as it is the complete work).

Solving that, you still will get 4 as the answer. Same logic you can apply.
Thank you.
(4)

Shushma Gulla said:   1 year ago
@All.

X - 40
X finished it in 8 days then 40 ÷ 8 = 5.
The efficiency of X is 1/5.
Total efficiency is 1, then Y = 1 - 1/5 = 4/5.
Y finished work in 16 days;
Y days efficiency is 5/4 (reciprocal of Y work efficiency).
Then Y =5/4×16 = 20.
X = 40, Y = 20.
Lcm is 40 (total work)
X is 1 unit, Y is 2 units
Together completed work X, Y is 40/3 = 13(1/3).

Rajvardhan Patil said:   3 months ago
X -> 40 days He work for 8 days 40-8 = 32.
Y -> 16 Days: That 32 days work Y complete in 16 days means Y is double as efficient than X,
So, assume X = 100,
Y is double efficient so Y = 200.
Total Work = 100 * 20/100 + 200(if X & Y work together),
So, the Ans is A.


Post your comments here:

Your comments will be displayed after verification.