Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
Answer: Option
Explanation:
(A + B)'s 20 day's work = | ![]() |
1 | x 20 | ![]() |
= | 2 | . |
30 | 3 |
Remaining work = | ![]() |
1 - | 2 | ![]() |
= | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 20 days. |
3 |
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
Discussion:
63 comments Page 6 of 7.
Praveen said:
1 decade ago
Consider 100% of the work can be completed by both A & B in 30 days, so this implies.
In 1 day A & B can complete 3.33% of work.
So A & B worked for 20 days which means they both completed 3.33*20 = 66.66% of work.
And now A alone need to finish 33.33% of work. But A finished in 20 days, which means.
A's Productivity is 1.66% per 1 day.
So A alone can complete it in = 60 days.
In 1 day A & B can complete 3.33% of work.
So A & B worked for 20 days which means they both completed 3.33*20 = 66.66% of work.
And now A alone need to finish 33.33% of work. But A finished in 20 days, which means.
A's Productivity is 1.66% per 1 day.
So A alone can complete it in = 60 days.
Godse said:
1 decade ago
a+b = 1/30.
a+b = x/20.
a = y/20.
So,
1/30 = x/20.
x = 20/30.
= 2/3.
Given,
x+y = 1.
y = 1-(2/3).
= 1/3.
Given,
a = y/20.
= 1/60.
So 60 days.
a+b = x/20.
a = y/20.
So,
1/30 = x/20.
x = 20/30.
= 2/3.
Given,
x+y = 1.
y = 1-(2/3).
= 1/3.
Given,
a = y/20.
= 1/60.
So 60 days.
Kaaly said:
1 decade ago
" very simple explanation "
Total work = (A+B) = 1/30.
B left the work = 1/20.
B -(A+B) = 1/20-1/30 = 1/60.
Total work = (A+B) = 1/30.
B left the work = 1/20.
B -(A+B) = 1/20-1/30 = 1/60.
Ars said:
1 decade ago
In question it self given that A did the remaining work in 20 days.
Sarvesh said:
1 decade ago
A and B together complete the work in 30 days.
So (A+B) 1 day work is (1/30).
B worked for 20 days & left, so A did the remaining 10 days effective work alone in another 20 days.
10 days remaining work ---> A took 20 days.
Therefore 30 days work(i.e 1 complete work) is done in----> (20/10)*30 = 60 days.
So (A+B) 1 day work is (1/30).
B worked for 20 days & left, so A did the remaining 10 days effective work alone in another 20 days.
10 days remaining work ---> A took 20 days.
Therefore 30 days work(i.e 1 complete work) is done in----> (20/10)*30 = 60 days.
Joel said:
1 decade ago
I have 145 days left to complete the construction project out of 442 louvers to install with 4 manpower. How many installed louver will they need to installed if they work for 8 hours a day and they can only 8.
Manikandan said:
1 decade ago
@kulbhushan
Already 20 days work finished by A and B.Remaining 10 days work done by A in 20 days. If A alone able to finish 30 days work in 60days.
Already 20 days work finished by A and B.Remaining 10 days work done by A in 20 days. If A alone able to finish 30 days work in 60days.
Kulbhushan said:
1 decade ago
Hi, how we calculated that 1/3 work in 20 days?
Avi said:
1 decade ago
A & B together works for 30 days
so, (A & B)'s 1 day work= 1/30
A&B worked for 20 days together
it is said after working together for 20 days b left
so, (A&B)'s work for 20 days together = (1/30)x20=2/3
remaining work that is to be done =1-2/3=1/3
1/3 work is done in 20 days
1 work i.e; complete work would be done in 20/(1/3)=20x3=60 days
so, (A & B)'s 1 day work= 1/30
A&B worked for 20 days together
it is said after working together for 20 days b left
so, (A&B)'s work for 20 days together = (1/30)x20=2/3
remaining work that is to be done =1-2/3=1/3
1/3 work is done in 20 days
1 work i.e; complete work would be done in 20/(1/3)=20x3=60 days
Dhruv said:
1 decade ago
How come 1/3 work is done in 20 days should the work in 20 days not be 2/3?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers