Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
40
50
54
60
Answer: Option
Explanation:

(A + B)'s 20 day's work = ( 1 x 20 ) = 2 .
30 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 20 days.
3

Therefore, the whole work will be done by A in (20 x 3) = 60 days.

Discussion:
63 comments Page 7 of 7.

Srishailam said:   1 decade ago
Am not understanding this problem any body please help me.

How A work come 20 days. Explain ?

Asha said:   1 decade ago
Hey @ankush

The question here is that in how many days A alone can do the entire work..

So its very simple 1/3 work done in 20 days, 2/3 work in 20*2=40 days and 3/3 (i.e. 1)= 20*3=60 days.

Ankush said:   1 decade ago
Now, 1 work is done by A in 20 days. 3 Therefore, the whole work will be done by A in (20 x 3) = 60 days.

Please can anyone explain me this.