Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
40
50
54
60
Answer: Option
Explanation:

(A + B)'s 20 day's work = ( 1 x 20 ) = 2 .
30 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 20 days.
3

Therefore, the whole work will be done by A in (20 x 3) = 60 days.

Discussion:
63 comments Page 1 of 7.

Abinesh said:   7 months ago
A + B = 30 days
Then A + B works for 20 days.
This shows that they have completed 2/3 works.
Now 1/3 of the work is done by A in 20 days.
So, 1/3 * 1/20,
= 60 days.
(4)

SamDon Sk said:   2 years ago
Assume painting a room A + B can complete in 30 days.
But they work for only 20 days and b left till now they have painted most of the room.
The remaining days left they can do work together is 10 days.
But A worked for 20 days to complete that 10 days of work MEANS.
A had worked DOUBLE days as they can work together.
So, A can alone can complete the work is DOUBLE of together work that is 30 * 2 = 60.
(28)

Anitha said:   2 years ago
A + B = 1/30
B only work 20 days after leaving;
B=1/20,
A+1/20 = 1/30
A = 1/20-1/30
A = 30-20/600
A = 10/600
A = 1/60
So, A Worked alone 60 days.
(44)

Ancy said:   2 years ago
A+B' s can finish work = 30 days
if,
A+B work together = 20 days
Therefore, 30:20 =3:2 (3 is the total work & 2 is together work)
= 3-2 = 1 (1 is remaining A's work)

A's remaining work is 20 days
= 20 * 3 = 60 days.
(18)

HB Rajputh said:   2 years ago
I'm not getting it, please help me by explaining in detail.
(5)

Piyush Srivastava said:   3 years ago
@All.

Here is the solution.

Together A + B takes 30 days to finish the work. So let us assume the total work to be 300 units(it can be any multiple of 30 to make the calculation easy) .

Therefore per day work efficiency of A+B together = 300/30 (work done = per day efficiency*time , so efficiency = work done/time taken) .

Thus A + B one day efficiency= 10 units.

Now ATQ, B left after 20 days, which means A + B worked together for 20 days. Therefore work done by A + B together in 20 days = 20 *10 = 200 (work done = one day efficiency * no of days worked )

Now remaining work = 300 - 200 = 100 units (total work - work done by A + B together)

Now A takes 20 days to finish the remaining work. Thus day efficiency of A = 100/20 = 5 units per day. ( Again using work done / time taken = per day work efficiency. Unitary method)
Thus per day efficiency of A = 5 units per day.

Now time is taken by A to finish the whole work alone = 300/5 = 60 days.. (total work / per day efficiency) . Hence A takes 60 days to finish the whole work alone.

Also, the people who want to know how much time will B take to do the whole work alone, the answer is again 60 days. Why?

Because per day efficiency of A + B together was 10 units, also after calculating A's per day efficiency was found out to be 5 units, thus B's per day efficiency= 10 - 5 = 5 units per day.

So it's the same as A, therefore B will also take 60 days to finish the whole work alone.
(10)

Sandip said:   3 years ago
Still, I can't understand this. Can anyone help me to get it?
(4)

Arun said:   3 years ago
Why the reaming work is -1? Explain it please.
(1)

Arun said:   3 years ago
a+b=30 days ==>1/30 amount of work in a single day.

a and b worked for 20 days, (1/30)*20 = 2/3.

after b left, a completed the remaining 1-(2/3)=>1/3 amount of work in 20 days.

------for 20 days-------
a will done 1/3==>0.33 amount of work.

------if its 40 days----
a will done 2/3==>0.66 amount of work.

------if its 60 days------
a will done 3/3==>1 amount of work.

So, the answer is, A will take 60 days to complete the total(ie:1) amount of work.

Hope this helps.
(7)

ATHI said:   4 years ago
In efficiency method;

A+B = 1/30.

(B only work for 20 days that mean A & B work together only 20 days. The remaining 20 days A alone do it).

Now,

A+B = 20 days
A (alone)= 20 days.

Total work:

20(A+B)+ 20(A) = 1, (1 IS TOTAL WORK )
20(1/30)+20A = 1,
(2/3)+20A = 1,
2+60A = 3,
60A = 3-2,
60A = 1.
A = 1/60.
i. e, A = 60days.
(5)


Post your comments here:

Your comments will be displayed after verification.