Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
40
50
54
60
Answer: Option
Explanation:

(A + B)'s 20 day's work = ( 1 x 20 ) = 2 .
30 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 20 days.
3

Therefore, the whole work will be done by A in (20 x 3) = 60 days.

Discussion:
63 comments Page 2 of 7.

Joel said:   4 years ago
Now total work=30 units.

A + B complete the 30 units of work in 30 days.

So, in one day they together complete 1 unit of work.

In 20 days, they complete 20 units of work.

Agree?

Now remaining work is 30 units-20 units=10 units is remaining which will be completed by A.

A takes 20 days to complete the remaining 10 units of work.
So he does 10/20= 1/2 unit of work in one day.
If A completes 1/2 unit of work in one day, then how many days he will take to complete the entire 30 units of work?

30/ (1/2) = 60 days.
(14)

Saloni panigrahi said:   5 years ago
E * t = w.

Since e is inverse of t so 20 becomes 1/20.
Now 1/20*t=1/3 since we have to find the time taken so,
T =20/1/3 HENCE T= 60 because in LHS it is multiplication so after coming to RHS it will divide.

Sinchana Shettar said:   5 years ago
Please, Explain this with LCM method.

Pankaj khatikkar said:   5 years ago
Can anyone explain this with LCM method?

Himanshu said:   5 years ago
Nice. Thanks all for explaining.

Bantu Venkatesh said:   6 years ago
Together 1/30*20=2/3.
2parts work completed.
Remaining 1 part 'A'completed in 20days.
1part work 20days.
3 prts --------?.
3 * 20 = 60 days.
(2)

Anuu said:   6 years ago
Good job @Kaaly.

Ashutosh said:   6 years ago
A and B together can complete a work in 30 day. They started together but after 6
days A left the work and the work is completed by B after 36 more days. A alone can complete
the entire work in how many days?
Please answer fast and answer is 90 btw ssc cpo question with answer that is 90.

Prabu said:   6 years ago
A and B together can complete a piece of work in 12 days. They worked together for 5 days and A alone finished the rest of the work in 14 days. An alone can complete the work in?

Sap said:   6 years ago
A and B together complete the project in 5 days. A alone can do the project in 8 days. How many days will B alone take to complete the same project? Can anyone solve this?


Post your comments here:

Your comments will be displayed after verification.