Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 10)
10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
Answer: Option
Explanation:
| (P + Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 37 | . |
| 8 | 10 | 12 | 120 |
| Work done by P, Q and R in 2 hours = | ![]() |
37 | x 2 | ![]() |
= | 37 | . |
| 120 | 60 |
| Remaining work = | ![]() |
1 - | 37 | ![]() |
= | 23 | . |
| 60 | 60 |
| (Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 11 | . |
| 10 | 12 | 60 |
| Now, | 11 | work is done by Q and R in 1 hour. |
| 60 |
| So, | 23 | work will be done by Q and R in | ![]() |
60 | x | 23 | ![]() |
= | 23 | hours 2 hours. |
| 60 | 11 | 60 | 11 |
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
Discussion:
96 comments Page 5 of 10.
Shiva said:
6 years ago
We can also do by this method,
Lcm of 8, 10 and 12 is 120.
Suppose total work is 120.
Then, 120/8 = 15.
120/10 = 12.
120/12 = 10.
Now above are respective capacities and we know that work = capacity x time
Hence we have,
15x2+12x+10x = 120.
22x = 90
x = 4 answer.
Lcm of 8, 10 and 12 is 120.
Suppose total work is 120.
Then, 120/8 = 15.
120/10 = 12.
120/12 = 10.
Now above are respective capacities and we know that work = capacity x time
Hence we have,
15x2+12x+10x = 120.
22x = 90
x = 4 answer.
Rohan said:
6 years ago
Why we didn't add the P's work at the end? Please explain.
Priyanka said:
5 years ago
As P works for 2hrs that is 9 am to 11am.
Consider for 2hrs
1lakh is done in 8hrs
2hrs..??
(2*100000)/8 = 25000.
Same for Q and R.
(2*100000)/10 = 20000 --->Q.
(2*100000)/12~~16000 --->R.
25000 + 20000 + 16000 = 61000.
In 2 hrs total books are printed are 61000
100000 - 61000 = 39000.
Remaining work is 39000.
Q+R work in 2hrs.
Q+R = 20000 + 16000 = 36000.
Approximately within 2hours Q and R can complete a work.
Consider for 2hrs
1lakh is done in 8hrs
2hrs..??
(2*100000)/8 = 25000.
Same for Q and R.
(2*100000)/10 = 20000 --->Q.
(2*100000)/12~~16000 --->R.
25000 + 20000 + 16000 = 61000.
In 2 hrs total books are printed are 61000
100000 - 61000 = 39000.
Remaining work is 39000.
Q+R work in 2hrs.
Q+R = 20000 + 16000 = 36000.
Approximately within 2hours Q and R can complete a work.
Gayathri said:
5 years ago
Total work needs to be completed = lcm (8,10,12) = 120 work.
Efficiency of P (work completed in 1 hr) = 120/8=15 work.
Similarly for Q=12 work and for R = 10.
Total work done by all the three in 1 hr =15+12+10 =37.
From 9 to 11 am all worked together ie. 37*2 =75 work completed out of 120.
Remaining work =120-75 = 45.
Work completed by Q and R in 1 hr = 10+12 =22.
Time taken to complete 45 work ==> 45/22 ~ 2 hrs.
ie.11 AM + 2 hrs ==> Around 1 PM work will be finished.
Efficiency of P (work completed in 1 hr) = 120/8=15 work.
Similarly for Q=12 work and for R = 10.
Total work done by all the three in 1 hr =15+12+10 =37.
From 9 to 11 am all worked together ie. 37*2 =75 work completed out of 120.
Remaining work =120-75 = 45.
Work completed by Q and R in 1 hr = 10+12 =22.
Time taken to complete 45 work ==> 45/22 ~ 2 hrs.
ie.11 AM + 2 hrs ==> Around 1 PM work will be finished.
Vishal R said:
5 years ago
I think we can do like this!
We need to find (Q+R) Work ! Since, We can write it as,
(Q+R ) = (P+Q+R ) - P ---> 1.
Therefore , P+Q+R = (1/8)+(1/10)+(1/12) = 37/120.
All of them Printed for 2 hrs, So (37/160) * 2 = 37/60.
Now find the Individual Work done by P,
P= (1/8), for 2 hrs (1/8)*2 = 1/4.
1--> (Q+R) = (37/60) - (1/4) = 11/30.
Therefore Taking, 30/11 = (approximately 2 hrs).
11 hrs + 2 hrs = 1 PM.
I hope this will be Easy to Understand!
We need to find (Q+R) Work ! Since, We can write it as,
(Q+R ) = (P+Q+R ) - P ---> 1.
Therefore , P+Q+R = (1/8)+(1/10)+(1/12) = 37/120.
All of them Printed for 2 hrs, So (37/160) * 2 = 37/60.
Now find the Individual Work done by P,
P= (1/8), for 2 hrs (1/8)*2 = 1/4.
1--> (Q+R) = (37/60) - (1/4) = 11/30.
Therefore Taking, 30/11 = (approximately 2 hrs).
11 hrs + 2 hrs = 1 PM.
I hope this will be Easy to Understand!
Sudharshan said:
9 years ago
I didn't understand @Sukanya.
Janie said:
5 years ago
The solution is;
10 - 8=2
12 - 10=2
So, two is a common difference.
Then, P is closed at 11:AM.
11:00 + 00:30 = 11:30.
Continued for four good times then you'll get 1:00PM.
10 - 8=2
12 - 10=2
So, two is a common difference.
Then, P is closed at 11:AM.
11:00 + 00:30 = 11:30.
Continued for four good times then you'll get 1:00PM.
Nav Raj Bhatta said:
4 years ago
Here,
P take a time to complete the work = 8 hours.
Q take the time to complete the work =10 hours,
R take the time to complete the work=12 hours,
One hour work by PQR=15+10+12 = 37.
Now LCM =120(total unit to complete) (120 unit means 100000).
Now time taken to complete 120 unit = 37*2 (9-11)+22 (11-12)+22(12-13)=120 unit completed till 1 AM.
P take a time to complete the work = 8 hours.
Q take the time to complete the work =10 hours,
R take the time to complete the work=12 hours,
One hour work by PQR=15+10+12 = 37.
Now LCM =120(total unit to complete) (120 unit means 100000).
Now time taken to complete 120 unit = 37*2 (9-11)+22 (11-12)+22(12-13)=120 unit completed till 1 AM.
Saurabh said:
4 weeks ago
Very easy approach.
Work to do (W) -> print 1 lakh books.
Machine P can do that work W in 8 hours.
Machine Q can do that work W in 10 hours.
Machine R can do that work W in 12 hours.
All machines started at 9 AM means all Machines P,Q and R are working together till 11 AM, meaning 2 hours together
So we write W/8 +W/10 +W/12, which together gives us per per-hour work (print) of each machine
->they did that together for two hours, so we multiply it by 2
2(W/8 + W/10 + W/12).
P is switched off at 11 AM means now remaining to machines Q and R will do the remaining work.
(W/10 + W/12)
But for how long these remaining machines are doing this remaining work, let's say x hours.
x(W/10 + W/12).
So total.
2(W/8 +W/10 +W/12) +x (W/10 +W/12) = W = total work.
solving for x , we get;
x ~= 2 hours.
Machines started from 9Am to 9Am + x time. So we get 1 AM as an Answer.
Work to do (W) -> print 1 lakh books.
Machine P can do that work W in 8 hours.
Machine Q can do that work W in 10 hours.
Machine R can do that work W in 12 hours.
All machines started at 9 AM means all Machines P,Q and R are working together till 11 AM, meaning 2 hours together
So we write W/8 +W/10 +W/12, which together gives us per per-hour work (print) of each machine
->they did that together for two hours, so we multiply it by 2
2(W/8 + W/10 + W/12).
P is switched off at 11 AM means now remaining to machines Q and R will do the remaining work.
(W/10 + W/12)
But for how long these remaining machines are doing this remaining work, let's say x hours.
x(W/10 + W/12).
So total.
2(W/8 +W/10 +W/12) +x (W/10 +W/12) = W = total work.
solving for x , we get;
x ~= 2 hours.
Machines started from 9Am to 9Am + x time. So we get 1 AM as an Answer.
Rahul said:
1 decade ago
All the machines are started at once.
we have got the solution as 4 hrs for both machines q & r
they have started at 9 a.m.
q & r work for 4 hrs
So 9+4=13 i.e,1 p.m.
we have got the solution as 4 hrs for both machines q & r
they have started at 9 a.m.
q & r work for 4 hrs
So 9+4=13 i.e,1 p.m.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers


2 hours.